Proposed Construction Of Sub Centre Including Health Wellness Centre At Block Mankapur At Patheeth Distt Gonda Up

Tendering Authority: Uttar Pradesh Projects Corporation Limited

India, Uttar Pradesh, Faizabad

NTID

29933879

Last Date For Submission

29 Nov, 2022

Closing Date

29 Nov, 2022

BOQ Items Total Items : 128 | Total Qty : 5658.609999999999
# Item Quantity Units
1 Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50m and lead upto 30m. and including filling, watering and ramming of excavated earth in to the space between the building and side of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by engineer in charge. 146.08 M3
2 Earth work in filling plinth 5.00 M3
3 Concrete with 40mm gauge Stone ballast, C/sand in 8:4:1 in foundation including supply of all materials labour and tools and plants etc. required for proper completion of work. 23.19 M3
4 Sand filling in the plinth including supply of necessary quality of sand from a distance not exceding 8.00 Km from the site of work and including watering and dressing etc. Rate includes cost of material labour and tools and plants etc. required for proper completion of work. 14.46 M3
5 Providing & injecting chemical emulsion for pre constructional antitermite treatment and creating a chemical barrier under and around the column pits wall trenches basement excavation top surface if plinth junction of wall and floor, along the external perimeter of binding expansion joints, surrounding of pipes and conduit etc., complete (plinth area of the building at ground floor only shall be measured as per IS-6313 Part II 1981)Aldrine emulisifiable concentrate or any other approved material such as Hepthachlor or Chlordance will be used. The rate of application of chemical emulsion shall be as follows- (I) Treatment for masonary & foundation 5 Ltr. per Sqm. (II) Back fill in immediate contact with foundation 7.5 Ltr.per Sqm. (III) Treatment of top surface of plinth filling 5 Ltr.per Sqm. (IV) Treatment of soil along external peri meter of building 7.50 Ltr. per Sqm. (V) Treatment of soil under apron along external perimeter 5 Ltr. per Sqm. 111.10 M2