Construction Of Main Storage T, Solan - Tender Details
Explore tender information for Construction Of Main Storage T in Solan, including eligibility, deadlines, and bid specifics.
Irrigation And Public Health Department
Solan, Himachal Pradesh, India
NTID 39435663
Opening Date : Thu 27th February, 2025
Closing Date : Thu 27th February, 2025
- ₹ 0.00
- NTID 39435663
Construction Of Main Storage Tank Of 25500 Ltr Cap In Village Sai Under Gwss Sai Tehsil Arki, District Solan Hp Sh Construction Of Rcc Main Storage Tank 25500 Ltr Cap. At Sai
Documents
Get Complete Tender Details Now – Download the Document!
Buy This Document-
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
-
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
Costs
-
EMD
5350.00 -
Document Cost
500.00 -
Estimated Cost
Refer Documents
BOQ Items Total Items : 16 | Total Qty : 841.67
# | Item | Quantity | Units |
---|---|---|---|
1 | Excavation in foundation, trenches etc. earth work in all type of soil such as pick work, jumper work, blasting work kankar,moorum singles including decomposed soft and hard rock etc. upto all heights stacking the excavated earth not more than 3 metres clear from the edge of excavation and then returning the stacked soil in 15cm layers when required into plinths and sides of foundation etc.consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated earth upto all leads and lifts as directed by the Engineer in charge complete in all respects. | 9.45 | Per Cubic meter. |
2 | Providing and laying cement concrete 1:3:6(1 Cement :3 Sand : 6 graded stone aggregate 20mm nominal size)and curing complete excluding the cost of form work in foundation and plinth including all carriage of materials upto all leads and lifts complete in all respects. | 3.62 | Per cubic meter |
3 | Providing and laying cement concrete work 1:1 :3 ( 1 Cement : 1 Sand : 3 graded stone aggregate 20mm nominal size) and curing complete excluding cost of form work and reinforcement for reinforced concrete work in :- | ||
4 | Foundations ,footings bases of columns and the like and mass concrete work i/c carriage of materials upto all leads and lifts complete in all respects | 2.38 | Per cubic meter |
5 | Walls any thickness (but not less than 0.10meter thickness including attached pilasters,buttresses plinth and string courses etc. from top of foundation(level) upto floor two level including all leads and lifts etc.complete in all respects. | 6.58 | Per cubic meter |

Purchase Access To Download Selected Documents
₹ 200
Select this Plan

For a one-time fee, you get unrestricted access to all documents and for a minimum of one year.